30 June 2008
McGraw Village Phase 1 (231 homes):
- Number of units by stage:
- McGraw Village Center is complete and turned over to Pinnacle
- Construction plans for Starbucks and Day Spa are complete
McGraw Village Phase 2 (233 homes):
- Number of units by stage:
- 133 units delivered
- 233 units in framing
- 233 units with poured slab
McGraw Village Phase 3 (132 homes):
- Number of units by stage
- 200 units abated and demolished
The Villages of Benning Welcome Center
- Welcome Center is complete and turned over to Pinnacle
- Pool and cabana construction is complete
Patton Village Phase 1 (238 homes):
- Number of units by stage:
- 182 units delivered
- 238 units in framing
- 238 units with poured slab
- 4 tot lots have been constructed
Patton Village Phase 2 (221 homes):
- Number of units by stage:
- 172 units in framing
- 221 units with poured slab
- Village Center is under construction
Patton Village Phase 3 (209 homes):
- Number of units by stage:
- 11 units with poured slab
Porter Village (37 homes):
- Number of units by stage:
- 7 units in framing
- 23 units with poured slab
East Main Post (Historic Units):
- 141 historic renovations completed
|


[ Click on photos for larger images ]
|