CONSTRUCTION UPDATE

30 June 2008

McGraw Village Phase 1 (231 homes):
  • Number of units by stage:
    • All 231 units delivered
  • McGraw Village Center is complete and turned over to Pinnacle
  • Construction plans for Starbucks and Day Spa are complete
McGraw Village Phase 2 (233 homes):
  • Number of units by stage:
    • 133 units delivered
    • 233 units in framing
    • 233 units with poured slab
    McGraw Village Phase 3 (132 homes):
  • Number of units by stage
    • 200 units abated and demolished
The Villages of Benning Welcome Center
  • Welcome Center is complete and turned over to Pinnacle
  • Pool and cabana construction is complete
Patton Village Phase 1 (238 homes):
  • Number of units by stage:
    • 182 units delivered
    • 238 units in framing
    • 238 units with poured slab
  • 4 tot lots have been constructed
Patton Village Phase 2 (221 homes):
  • Number of units by stage:
    • 172 units in framing
    • 221 units with poured slab
  • Village Center is under construction
Patton Village Phase 3 (209 homes):
  • Number of units by stage:
    • 11 units with poured slab
Porter Village (37 homes):
  • Number of units by stage:
    • 7 units in framing
    • 23 units with poured slab
East Main Post (Historic Units):
  • 141 historic renovations completed




[ Click on photos for larger images ]